1: Initial Operations Challenges

  • To help the City respond to multiple NPDES permit violations, Alliance was initially asked to supply a corrective action team of experienced, licensed plant operators on an emergency basis to bring the plant into compliance within a critical eight-week timeframe.
  • An enforcement action and a building moratorium necessitated quick and continuing improvements in effluent quality.
  • To safeguard the integrity of the City’s wastewater collection and treatment process, the City needed to identify more effective ways of managing the wastewater streams from two correctional facilities, the 2,600-bed medium security Western Missouri Correctional Center and the 1,500-bed maximum security Crossroads Correctional Center.

2: Project Background

The Cameron wastewater treatment plant is an oxidation ditch facility which utilizes grit removal, screening, and secondary clarification prior to sludge dewatering and digestion.

Plant facilities were substantially upgraded in 1993, and in 1996 the plant underwent a major expansion program that doubled its size to 1.6 mgd. In an effort to build support for bond issues to finance these projects, Alliance led a community involvement effort that included numerous public meetings, the development of informational materials, and other awareness activities. Both bond issues passed by majorities as high as 80 percent.

During the design phase of these improvement projects, Alliance acted as the City’s technical representative, reviewing all engineering plans, and making numerous recommendations that would result in further cost-savings, improved operating efficiencies, and a better quality end product. Alliance determined, for example, that a second headworks structure was not necessary, resulting in a cost savings of more than $50,000.

3: Alliance Achievements

  • Immediately after coming on board, an emergency crew of Alliance plant operators improved the plant effluent quality and soon had the City’s plant operating in full regulatory compliance.
  • Alliance assisted the City on negotiating a “reasonable” consent decree with regulatory officials. Alliance operated the facilities through the consent decree period without any violations and allowed for the City’s continued growth. Since then, Alliance has successfully guided the plant through two major upgrade and expansion programs.
  • A successful biosolids program brought on-stream by Alliance provides for beneficial reuse of the wastewater byproduct on agricultural land.
  • Alliance has advised and assisted the City in negotiations with the correctional centers for pretreatment of their high strength waste.
  • The Cameron Plant was nominated for the Missouri Water Environment Association’s Treatment Plant of the Year (in the large facility category) for 2000.
  • Alliance’s Plant Manager for Cameron received the Missouri Water Environment Association’s Plant Operator of the Year for 2000.
  • The Alliance Cameron Division received the 2001 “Governor’s Award for Environmental Excellence and Pollution Prevention” for efforts in education and outreach.
  • The Cameron Plant received the Missouri Water Environment Association's Biosolids Management Award for 2003.
  • Wastewater staff collect data and manage odor complaints with the goal of participating in an odor study. The study will focus on odor dispersion modeling to discover plant improvements to reduce odor in this fast growing community.
  • Converting all fields in the land application program to a GPS field mapping system is the most recent project for the City. The end result will provide better monitoring of nutrient inputs/outputs and maintain accurate soil test site locations as well as better define buffer zones and other useful applications.
  • Alliance performed a use attainability analysis (UAA) in preparation for upcoming regulatory requirements in 2005.